Calculate markup percentage, overhead recovery, gross profit margin, and final bid price. Understand the critical difference between markup and margin so you never underbid a job.
Markup and margin sound interchangeable but are calculated differently, and confusing them is one of the most common ways contractors underprice jobs and lose money. Markup is profit expressed as a percentage of cost. Margin (gross margin) is profit expressed as a percentage of revenue. The same dollar amount of profit gives you a higher markup percentage than margin percentage.
Markup: Selling Price = Cost × (1 + Markup%)
Margin: Selling Price = Cost ÷ (1 − Margin%)
Key insight: A 25% markup = 20% gross margin. A 33% markup = 25% gross margin. If you want a 25% margin, you need a 33% markup, not 25%.
| Markup % | Gross Margin % | Example: $10,000 Cost | Profit |
|---|---|---|---|
| 10% | 9.1% | $11,000 | $1,000 |
| 20% | 16.7% | $12,000 | $2,000 |
| 25% | 20.0% | $12,500 | $2,500 |
| 33% | 25.0% | $13,300 | $3,300 |
| 43% | 30.0% | $14,300 | $4,300 |
| 50% | 33.3% | $15,000 | $5,000 |
Overhead covers all costs of running your business that don't tie to a specific job. If you don't recover overhead on every job, those costs come directly out of your profit. Overhead is not optional; it's a real cost that must be included in every bid.
Most residential GCs run 15–20% overhead as a percentage of revenue, which is a similar but not identical figure to overhead expressed as a percentage of direct cost. This calculator's Overhead Rate field uses the direct-cost basis (matching the industry-common "cost-plus" convention): divide your annual overhead cost by your annual direct job costs, not by revenue, and enter that percentage. If you only know your revenue-based overhead ratio, convert it first, since the two bases produce different numbers for the same underlying business.
Materials (lumber, hardware, concrete): $4,200
Direct labor (2 carpenters × 3 days × $45/hr × 8 hrs): $2,160
Total direct cost: $6,360
+ 18% overhead recovery (on direct cost): $6,360 × 0.18 = $1,145 → running total $7,505
+ 10% contingency (also on direct cost, not on the running total): $6,360 × 0.10 = $636 → total cost $8,141
+ 20% profit margin (on revenue, so divide by 1 − 0.20): $8,141 ÷ 0.80 = $10,176 bid price (equivalent to a 60% markup on direct cost)
| Project Type | Typical Markup Range | Notes |
|---|---|---|
| Residential remodel (GC) | 20–35% | Higher for complex or high-risk work |
| Specialty trade (plumbing, electrical) | 25–40% | Higher overhead due to licensing/insurance |
| New construction (GC) | 15–25% | Lower markup, higher volume |
| Service calls / small jobs | 30–50% | High overhead per dollar of revenue |
| Materials only (pass-through) | 10–20% | Covers procurement time and carrying cost |
The Profit Margin Target field is the number contractors most often set carelessly, either copying a competitor's advertised rate or defaulting to "whatever feels fair." Both approaches ignore the fact that your target margin should reflect your specific risk, capital needs, and growth plans, not an industry rumor.
A reasonable starting point for most residential contractors is 8–15% net profit margin, calculated on revenue after overhead is already recovered. Within that range, several factors push the number up or down:
Whatever target you settle on, apply it consistently. A margin that swings job to job based on gut feel makes it impossible to know whether your business is actually profitable at the end of the year, since some jobs will have quietly subsidized others.
Change orders (added or modified scope requested after the contract is signed) are one of the most commonly under-priced items in residential construction. Contractors who are diligent about markup on their original bid frequently price change orders at raw cost, treating them as a favor to keep the client happy rather than as new work that carries the same overhead and profit obligations as anything else on the job.
The math is straightforward: a change order should carry the same markup structure as the original bid. If your baseline bid included an 18% overhead recovery and a 20% profit margin, a $500 change order in materials and labor should be priced the same way, not handed over at $500 flat. Skipping markup on change orders doesn't just cost the missed profit on that specific item; it also fails to recover the real overhead cost of managing the change (revised drawings, additional coordination, potential schedule disruption).
A useful practice is to have a standard change order markup percentage written into your contract up front, so pricing changed work isn't a negotiation every time. This also protects the relationship with the client, since the markup was agreed to before any change was requested rather than appearing to be sprung on them mid-project.
For related estimating tools, see our labor cost calculator, our material waste calculator, and our construction cost calculator. For a broader walkthrough of pricing a full job, see our project cost estimation guide.