Free Construction Tool

Excavation Calculator

Reviewed and updated: August 2026

Calculate cubic yards of excavation, total cost, haul-away loads, and truck trips for any digging project, pools, foundations, basements, drainage, and site grading.

ft
ft
ft
0 = vertical walls; 1 = 1:1 slope adds depth ร— 1 ft to each side
ft
ft
ft
ft
Working room around pool shell: typically 2 ft
ft
ft
ft
Maximum depth removed at the high end
ft
Fill = dirt needed to raise the low end (not hauled away)
ft
$5โ€“$15 typical; $50โ€“$200 for rock
$
$
YOUR RESULTS
Bank Volume
โ€”
cu yd (in ground)
Loose Volume
โ€”
cu yd (trucked)
Truck Loads
โ€”
loads
Weight
โ€”
tons (approx)
Dig Cost
โ€”
est.
Haul-Away Cost
โ€”
est.
Total Estimate
โ€”
est.
โš ๏ธ Call 811 before digging, underground utilities must be marked 2โ€“3 business days in advance. Cost estimates use national averages. Rocky soil, limited access, or deep excavations can increase costs 2โ€“5ร—. Always get 3 quotes from licensed excavation contractors.

Choose your excavation shape: rectangular (foundations, basements, trenches), pool (with shallow-to-deep grading and working clearance), or slope/grading (cut-and-fill site work). Enter your soil type to apply the correct swell factor, then add your cost rates for a complete estimate. Bank volume is what's in the ground; loose volume is what gets trucked. Always use loose volume for haul-away pricing.

How to Calculate Excavation Volume

Bank volume = length ร— width ร— depth รท 27 (cubic feet to cubic yards). This is the in-ground volume. When soil is excavated it expands: this is called swell. The loose volume (what actually goes into the trucks) is always larger than the bank volume. Use bank volume for excavation pricing; use loose volume for haul-away and truck count estimates.

Worked example: a 30ร—20 ft foundation excavation, 4 ft deep, vertical walls, average loam (25% swell). Bank volume = 30 ร— 20 ร— 4 รท 27 = 88.9 cu yd. Loose volume = 88.9 ร— 1.25 = 111.1 cu yd. At a 14 cu yd truck: 8 truck loads. At $8/cu yd dig + $12/cu yd haul: dig cost = $711, haul cost = $1,333, total โ‰ˆ $2,044. Add a contingency for rock if uncertain about subsurface conditions.

Soil Type and Swell Factor Reference

Soil TypeSwell FactorWeight (bank cu yd)Digging Difficulty
Loose / sandy soil1.20 (20%)~2,400โ€“2,700 lbsEasy, hand-dig possible
Average loam / topsoil1.25 (25%)~2,700โ€“3,000 lbsModerate, standard equipment
Dense clay1.30 (30%)~3,000โ€“3,400 lbsHard, may need hydraulic breaker
Hardpan / caliche1.40 (40%)~3,200โ€“3,800 lbsVery hard, blasting sometimes required
Shattered rock1.50 (50%)~4,000โ€“5,000 lbsExtremely hard, 5โ€“10ร— cost premium

Excavation Cost Reference

Project TypeDig Cost (per bank cu yd)Haul-Away (per loose cu yd)Typical Total Range
Standard soil, good access$5โ€“$15$8โ€“$20$13โ€“$35 per cu yd all-in
Clay / difficult soil$15โ€“$35$10โ€“$25$25โ€“$60 per cu yd all-in
Rock excavation$50โ€“$200+$20โ€“$40$70โ€“$250+ per cu yd all-in
Pool excavation (avg)$1,500โ€“$5,000Included or separateFlat bid; get 3 quotes
Basement (full)$10,000โ€“$30,000Often includedVaries enormously by depth/soil
Foundation footings only$500โ€“$3,000Often includedUsually flat bid

Choosing the Right Equipment

Equipment choice affects both cost and how much of a footprint the job leaves behind. Contractors size equipment to the job rather than always using the biggest machine available:

EquipmentTypical UseBucket/Capacity
Mini excavator (1 to 4 ton)Tight-access yards, utility trenches, small footings0.5 to 6 cu ft bucket
Standard excavator (8 to 20 ton)Foundations, basements, pools1 to 3 cu yd bucket
Skid steerGrading, backfill spreading, material moving0.5 to 1 cu yd bucket
Backhoe loaderUtility trenches, small-to-mid excavation0.5 to 1.5 cu yd bucket
BulldozerLarge-area grading, land clearingBlade width, not bucket-rated

Tight side-yard or backyard access is one of the most common reasons a bid comes in higher than expected: a standard excavator that can't fit through a gate forces the contractor to use a smaller mini excavator and haul spoil by hand or wheelbarrow to a truck, which adds significant labor time. If your access is narrow, mention it when requesting quotes so the bid reflects the actual equipment needed.

Bank vs. Loose vs. Compacted Measure

Every excavation project deals with three volume states: bank measure (soil in the ground; used for contract pricing), loose measure (soil after it's dug; expands due to air voids and is used for truck count and haul-away pricing), and compacted measure (soil after re-compaction; shrinks below even bank volume and is used when calculating backfill). This calculator handles bank and loose volumes automatically. If you need to backfill, assume compacted volume is 80โ€“90% of the bank volume.

The diagram below shows how the same soil takes up different amounts of space at each stage.

SAME SOIL, THREE DIFFERENT VOLUMES Bank 100% (in ground) Loose 120 to 150% (trucked) Compacted 80 to 90% (backfill)

Bank volume is what you're billed for digging. Loose volume, the swelled state, is what gets trucked away.

Common Excavation Mistakes

Contractor tip: Always get at least 3 competitive bids for any excavation job over $2,000. Ask each contractor what happens if they hit rock: is it a fixed per-yard rock rate or a time-and-materials charge? Also ask whether the haul-away destination is a licensed fill site (required for clay and contaminated soil) or a private property disposal. Unlicensed disposal creates liability that can follow the property owner for years.

Planning a related project? See our concrete guide and project cost estimation guide.

Frequently Asked Questions
How much does excavation cost per cubic yard? โ–พ
Standard soil excavation runs $5 to $15 per bank cubic yard in most US markets (2026), not including haul-away. Clay and difficult soil runs $15โ€“$35 per yard. Rock excavation is $50โ€“$200+ per yard. Haul-away (trucking + landfill fees) adds $8โ€“$25 per loose cubic yard. Minimum charges are typically $500โ€“$1,500 even for small projects. Prices vary enormously by region, always get at least 3 quotes from licensed excavation contractors.
How many cubic yards does a dump truck hold? โ–พ
A standard single-axle dump truck holds 10โ€“14 cubic yards of loose soil. A tandem-axle dump truck holds 14โ€“16 yards. Semi end-dumps hold 18โ€“22 yards. Contractors count truck loads to estimate haul-away costs: divide your loose volume by truck capacity and round up. For a 30ร—20ร—4 ft foundation with average loam: 111 loose cu yd รท 14 cu yd per truck = 8 truck loads.
Do I need a permit for excavation? โ–พ
Yes, for most structural excavation: pool excavation, basement digging, foundation work, and any trench over 5 feet deep require permits in most jurisdictions. Trenches over 5 ft also require OSHA-compliant shoring or sloping, which dramatically increases the footprint (and volume) of the excavation. Always call 811 at least 2โ€“3 business days before digging to have underground utilities marked. Striking a gas or electrical line during excavation can be fatal and results in major liability.
What is soil swell and why does it matter? โ–พ
Soil swell is the volume increase that occurs when soil is excavated and broken up. Compacted soil in the ground contains minimal air voids; once dug, the particles don't compact back together and the volume expands 15โ€“50% depending on soil type. This matters because: (1) you'll need more trucks than the bank volume suggests, and (2) haul-away is typically priced per loose yard. A 100 bank-yard job generates 125 loose yards of average soil: 8 to 9 truck loads at 14 yards per truck, not 7.
How much excavation does a pool require? โ–พ
A typical 32ร—16 ft pool with a 3.5 ft shallow end and 8 ft deep end requires roughly 175 to 190 bank cubic yards of excavation, including 2 ft of working clearance around the shell and 1 ft of working room below the shell. At 25% swell, that's roughly 220 to 240 loose cubic yards, about 16 to 17 truck loads at 14 cu yd per truck. Pool excavation typically costs $1,500 to $5,000 as a flat bid; rock-heavy sites can cost significantly more. The pool contractor's quote usually includes excavation, confirm this before signing the contract.