Concrete Guide

Concrete Quantity Guide: How Much to Order and Why

Running short of concrete mid-pour is one of the worst things that can happen on a job site. Here's how to calculate accurately, what to add for waste, and why small orders cost more than you'd expect.

Concrete & Masonry · BuildItCalc.com

The math for calculating concrete isn't complicated. Length times width times depth, divide by 27, add waste — done. What causes problems is the stuff around the math: uneven subgrades, forms that aren't as square as they look, the ready-mix truck that shows up with exactly what you ordered and not a yard more. This guide covers the calculation and the real-world context that the calculation misses.

Want the number fast? Use the calculator — then come back here to understand what it's telling you.

Concrete Calculator →

The Basic Calculation

Concrete volume is measured in cubic yards. One cubic yard is 3 ft × 3 ft × 3 ft = 27 cubic feet. The formula:

Cubic yards = (length × width × thickness in feet) ÷ 27

Thickness is always in feet, not inches. A 4-inch slab is 4 ÷ 12 = 0.333 feet. A 6-inch slab is 0.5 feet. This is where the first calculation errors happen — people leave thickness in inches and get a number that's 12 times too large.

WORKED EXAMPLE — 12×20 FT DRIVEWAY APRON

Length: 20 ft | Width: 12 ft | Thickness: 6" (0.5 ft)

Volume = 20 × 12 × 0.5 = 120 cubic feet

120 ÷ 27 = 4.44 cubic yards

Add 10% waste: 4.44 × 1.10 = 4.88 cubic yards

Order 5 cubic yards

Always round to the nearest half yard. Most plants won't sell fractions smaller than 0.5 CY.

Waste Factor — Why You Always Need More Than the Math Says

The theoretical volume is what you'd need if your forms were perfect, your subgrade was perfectly flat, and nothing spilled. None of those things are ever true. Add waste for:

Project TypeWaste FactorWhy
Flat slab, good forms5–8%Minor subgrade variation
Slab on uneven ground10%Low spots consume significantly more concrete
Footings and walls10–15%Form movement, irregular trench walls
Post holes15–20%Hole diameter varies; soil crumbles
Stamped or decorative10%Thickness variation from hand finishing

Ready-Mix vs. Bagged — The Decision Nobody Talks About Honestly

Ready-mix concrete is delivered by truck and is the right choice for anything over about 1 cubic yard. But there's a catch: most ready-mix plants have a minimum order of 1 yard, and many charge a short-load fee for orders under 3–4 yards. A 1-yard order might cost $200–$250 in concrete plus a $100–$150 short-load fee, making the effective cost $350 per yard — compared to $100–$130 per yard for a full truck.

For small jobs (under 0.5 yards), bagged concrete is usually more practical. An 80 lb bag yields about 0.6 cubic feet. You need 45 bags for 1 cubic yard. At $6–$7 per bag, that's $270–$315 per yard in materials — more expensive than ready-mix but with no minimum and no delivery fee.

Volume NeededBest OptionRough Cost
Under 0.5 CY80 lb bags$150–$200
0.5–1.0 CYBags or ready-mix with short-load fee$200–$400
1–3 CYReady-mix (short-load fee likely)$300–$700
Over 3 CYReady-mix (full truck rate)$400–$900+

Thickness Matters More Than Area

This is worth emphasizing because it surprises people. Doubling the area of a slab doubles the concrete needed. But doubling the thickness also doubles it — and thickness has a much bigger effect on structural performance. A 4-inch slab is standard for sidewalks and residential slabs with foot traffic only. A 6-inch slab handles vehicles. An 8-inch slab handles heavy trucks. Going from 4 to 6 inches adds 50% more concrete. Going from 4 to 8 inches doubles it. Don't skimp on thickness to save on concrete — it's the wrong place to cut costs.

Common Mistakes When Ordering Concrete

💡 One rule that works: Calculate your volume, add 10%, then round up to the nearest half cubic yard. If the resulting number feels like you're over-ordering, you're probably right where you should be. The cost difference between 4.5 and 5 yards of ready-mix is $50–$75. The cost of running short — calling for a partial load, waiting for the truck, hand-mixing bags to finish — is a half day of your time and a cold joint in your slab.